LMNT Linear audit — 2026-04-09 (Team LMNT vs SOW Exhibit A)

SOW reference

LMNT x BrainForge Data Sprint — Term Apr 1–Aug 31, 2026. Five workstreams:

  1. Data Foundation & Governance
  2. Demand Performance Visibility
  3. Marketing Visibility
  4. Supply Chain Visibility
  5. BI & Self-Service Enablement

Pre-alignment state (summary)

TypeCountNotes
Initiatives (LMNT-named)8Framed as “Option B” domains (Data Modeling, Ingestion, Reporting, Documentation, Adoption, Omni Plan, VP Strategy, retired Supply Chain) — not 1:1 with SOW workstreams
Projects (team LMNT, first page)20Spread across those initiatives; Supply Chain Data Mart sat under Data Modeling
RiskDuplicate initiative taxonomy vs signed SOW; onboarding not under WS1

Mapping applied (post-alignment)

SOW WSInitiative namePrior initiative (id)
WS1LMNT | SOW — WS1 Data Foundation & GovernanceLMNT | Documentation
WS2LMNT | SOW — WS2 Demand Performance VisibilityLMNT | Data Modeling
WS3LMNT | SOW — WS3 Marketing VisibilityCreated
WS4LMNT | SOW — WS4 Supply Chain VisibilityLMNT | Supply Chain (reactivated)
WS5LMNT | SOW — WS5 BI & Self-Service EnablementLMNT | Omni Plan

Retired (Completed) after project moves: LMNT | Ingestion, LMNT | Reporting and Analytics, LMNT | Adoption, LMNT | VP Level Strategy — projects reassigned to WS2 or WS5.

Invariants (north star)

  • Every issue → project
  • Every project → one of the five initiatives
  • Every initiative → ≥1 milestone (via project milestones)

Team onboarding (Garrett ramp / PM): project under WS1, not a sixth initiative.

Post-alignment (2026-04-09)

  • Five initiatives renamed/created; projects reassigned; Team onboarding project created under WS1.
  • Retired initiatives completed: Ingestion, Reporting and Analytics, Adoption, VP Level Strategy.
  • Orphan issues (no project) addressed for sampled backlog; re-run filters periodically.
  • Vault: lmnt-linear-sow-alignment-2026.md, lmnt-linear-handoff-garrett.md, PDF in repo.