Meeting Title: Zoom Meeting Date: 2025-03-24 Meeting participants: Aakash Tandel, Nicolas Sucari, Amber Lin


WEBVTT

1 00:00:19.860 00:00:20.909 Nicolas Sucari: Hey! Amber.

2 00:00:21.970 00:00:22.800 Amber Lin: Hi

3 00:00:24.290 00:00:25.320 Nicolas Sucari: Can you hear me?

4 00:00:25.320 00:00:26.760 Amber Lin: Yeah, I can hear you.

5 00:00:27.610 00:00:28.670 Nicolas Sucari: Hey! How are you?

6 00:00:29.080 00:00:34.029 Amber Lin: I’m good this is for the app that we showed on Monday, right

7 00:00:34.590 00:00:36.020 Nicolas Sucari: Yep, yeah.

8 00:00:36.730 00:00:43.140 Nicolas Sucari: The idea was to share with you and Akash a little bit on how to set that up and how we’re using that

9 00:00:43.649 00:00:50.600 Nicolas Sucari: I mean, I don’t have like anything new from Monday, but I wanna go deep and answer any questions you and the cash have

10 00:00:51.330 00:00:52.320 Amber Lin: Oh, okay.

11 00:00:53.400 00:00:56.080 Nicolas Sucari: If you’re if you’re really busy with something else, we can reschedule

12 00:00:56.080 00:01:04.589 Amber Lin: No, I’m not busy. I I’m not. I don’t have any meetings. I’m just working on the different 5 projects. So I have. I have time

13 00:01:05.630 00:01:07.020 Nicolas Sucari: Okay, that’s fine.

14 00:01:08.600 00:01:09.720 Nicolas Sucari: Hey? Akash!

15 00:01:10.290 00:01:11.209 Aakash Tandel: Hey? How’s it going

16 00:01:12.550 00:01:13.570 Nicolas Sucari: All good.

17 00:01:14.250 00:01:19.289 Nicolas Sucari: Okay? So I don’t know what have. Even, it’s not with us anymore. Right?

18 00:01:21.090 00:01:22.239 Nicolas Sucari: Okay, cool.

19 00:01:23.330 00:01:49.019 Nicolas Sucari: cool. The idea of this meeting, as I said, was just to go through operating. Try to share a little bit how I set it up. And so that you guys know how to look at the information that is there. I know we shared these on Monday. But yeah, maybe it was not not like the best place for questions, or to deep diving on on the app. So any question you have, please ask me.

20 00:01:50.020 00:01:51.199 Nicolas Sucari: I’m gonna share.

21 00:01:51.560 00:01:55.199 Nicolas Sucari: Okay, let me know if you’re seeing. Yeah, right? Okay?

22 00:01:56.290 00:01:59.259 Nicolas Sucari: So operating has

23 00:02:00.040 00:02:06.570 Nicolas Sucari: has different views. 3 different or or 4 4. Yeah, 4 different views that we can use.

24 00:02:06.680 00:02:24.449 Nicolas Sucari: 1st of all, is horizon like, this is where we can kind of create different projects ahead of time, like before starting to work on those projects and start to kind of assigning roles of team members that we’re gonna need for these kind of projects. Right.

25 00:02:24.650 00:02:25.660 Nicolas Sucari: For example.

26 00:02:25.910 00:02:40.940 Nicolas Sucari: here we have all of the projects that we are, we we already started using. And where we have, like all of our team members added to them, and we have some others that we don’t have team yet. For example, sales sales is an internal project.

27 00:02:40.940 00:02:57.600 Nicolas Sucari: but we can create the project. We can add a description. We can add a project owner and groups of of people. And we can plan like when it’s gonna start and when it’s gonna end. And then we can kind of set up the team that we’re gonna use. For example, if I add someone here, I can use the role.

28 00:02:58.180 00:03:00.629 Nicolas Sucari: Let’s say I’m gonna add a protoner.

29 00:03:00.820 00:03:29.419 Nicolas Sucari: And I I don’t need to add the person if I don’t have like defined yet. Which who is gonna be joining as a product owner in this kind of project. And then I can click, suggest and all there are. Yeah, I can get this suggestion of all of the product owners that we have, and what is the assignation? And what is the allocation that they have free, so that they can spend in this project. And I can kind of decide which one I’m gonna use for

30 00:03:29.490 00:03:31.439 Nicolas Sucari: or kind of these projects. Right?

31 00:03:31.520 00:03:37.760 Nicolas Sucari: So let’s say, sales. Robert is doing most of the sales stuff, so I can assign Robert. I can click, assign

32 00:03:38.660 00:03:39.440 Nicolas Sucari: right?

33 00:03:40.560 00:04:08.470 Nicolas Sucari: So right now I scheduled. I I added Robert to the sales project that is started on 1st of January this year. And but I I haven’t added kind of how many hours he’s gonna be working on in this project. So this timeline view is where we add, like the detail of how many hours a week, or what is the percentage of allocation of each team member. In each of the different projects we have 3 different views only project.

34 00:04:08.720 00:04:10.819 Nicolas Sucari: So we can see all here on the left.

35 00:04:11.208 00:04:16.630 Nicolas Sucari: People. We change from projects to the detail for people. And we have the split view.

36 00:04:16.950 00:04:32.650 Nicolas Sucari: Just to kind of look at this, we can filter out stuff or like projects or people if we want. But if not, we can just use kind of this view to check both things, projects, and people. So let’s go to the sales ones that I already added. Here, Robert, you see.

37 00:04:32.650 00:04:52.699 Nicolas Sucari: we have the sales project with Robert in in it, but it doesn’t say how many hours is Robert kind of spending in this project? Right? So if I click on this project, I can see here, Robert, that doesn’t have like any allocation to this project. And if I click here, for example, it’s gonna let’s say it’s gonna start

38 00:04:52.710 00:05:10.059 Nicolas Sucari: tomorrow. I can add, like 100% of allocation. That’s 20 HA week from Robert, or I can add 20%. That’s 4 HA week, or I can do the other way, not like 10 HA week and say, Okay, it’s gonna be like, 50% on allocated on sales stuff, right?

39 00:05:10.510 00:05:20.420 Nicolas Sucari: I can add the start date and end date. So let’s say, he’s been working on 50% since January first.st And let’s leave it open ended and I can hit save.

40 00:05:20.550 00:05:29.570 Nicolas Sucari: And that will let us know that here Robert has 50% of his time, that is, 20 HA week allocated to

41 00:05:29.860 00:05:31.780 Nicolas Sucari: to the sales project right?

42 00:05:32.010 00:05:44.900 Nicolas Sucari: What I did with sales project. This is internally, this is not billable, because I set it up like like that. But we can do it for all other projects. So yeah, I don’t know why it got stuck here. But let me refresh this.

43 00:05:46.420 00:05:49.649 Nicolas Sucari: And yeah, and I kind of allocated all of these.

44 00:05:51.220 00:05:58.819 Nicolas Sucari: oh, I look at it all the time from each of the team members into all of the projects utam shared some

45 00:05:58.950 00:06:04.159 Nicolas Sucari: details of how to do that like which, how, how how much hours, is gonna

46 00:06:04.450 00:06:09.780 Nicolas Sucari: everyone is gonna spend on each of these projects. And yeah, I kind of

47 00:06:09.940 00:06:17.629 Nicolas Sucari: just set that up. And I want you to guys review and see if if that is okay, and also we can compare with the

48 00:06:17.830 00:06:30.509 Nicolas Sucari: clockify tracking our struggling that everyone is doing. How did I do that? I just kind of exported from clockify. I’m brought it back here. I don’t know why, but this got stuck. Give me a minute.

49 00:06:31.180 00:06:33.529 Nicolas Sucari: Wait. Where are we here?

50 00:06:33.760 00:06:43.439 Nicolas Sucari: Okay, yeah, that’s it. So for example, ABC, amber, so we added, like you as a project manager, and then we have Casey Miguel and Patrick.

51 00:06:43.500 00:07:09.739 Nicolas Sucari: Patrick is spending 100. This is for 40 HA week. I don’t know if this is correct. I don’t know if he’s working so many hours, and we can change that if 40 HA week is not like he’s kind of standard. We have Miguel here that has yeah, a 25% of 40 HA week. That’s 10 HA week. Right? We have Casey. Same, I guess. Yeah, 10 HA week. And we have you here at 10 HA week. Okay.

52 00:07:10.400 00:07:17.540 Nicolas Sucari: if I needed to change like Patrick designation here, I can go to edit and change this the time right

53 00:07:17.970 00:07:19.379 Nicolas Sucari: and hit save.

54 00:07:19.870 00:07:32.089 Nicolas Sucari: I’m not gonna do that. But if I’m if I then need to change like. How many hours a week is Patrick working? I need to go to the Directory, where we have, like all of the people and go to Patrick. Here, let’s say.

55 00:07:32.502 00:07:41.509 Nicolas Sucari: I can see here. Okay, he’s working 10 h, it was. And and I added, like an individual kind of working hours. And he’s gonna be working like 10 HA week. Right?

56 00:07:41.923 00:07:46.620 Nicolas Sucari: So if I go back to timeline, I need to, I guess, refresh this one.

57 00:07:48.520 00:07:54.029 Nicolas Sucari: The tool has some kind of issues yet. But we are kind of doing all of these. Yeah, I don’t know why this is.

58 00:07:56.010 00:08:01.170 Nicolas Sucari: Let me do. Okay, maybe it’s because of the times when it started.

59 00:08:02.357 00:08:10.300 Nicolas Sucari: But yeah, I’m still kind of setting up. When is everyone start like this, start date and end date. Okay, employment. Start 14 of March.

60 00:08:10.440 00:08:13.670 Nicolas Sucari: And let me see here, okay, perfect.

61 00:08:16.740 00:08:20.829 Nicolas Sucari: Okay, this is the issue. If I go. This I can hit save.

62 00:08:21.910 00:08:35.889 Nicolas Sucari: And now we can say, okay, he started on 14. That’s when he started working on Brainforge. Right? So that’s the employment start date. And the and I added, like the same project start date here. So now we can see that this amount of hours

63 00:08:36.230 00:08:37.790 Nicolas Sucari: are the ones that we

64 00:08:38.159 00:08:44.659 Nicolas Sucari: yeah, it got stuck again. The tool is not great had some issues and bugs. But I don’t know why it’s this happening

65 00:08:45.550 00:08:47.050 Nicolas Sucari: you see here on my screen.

66 00:08:47.190 00:08:48.260 Nicolas Sucari: It’s crazy right

67 00:08:49.699 00:08:50.869 Amber Lin: I see that

68 00:08:51.270 00:09:05.599 Nicolas Sucari: It’s strange. Okay, that’s it. But yeah, that’s how I set it up for all of the projects. So we have ABC Akash. I added you in internal. But now that Steven is not here, maybe we need to move you to the the other projects right

69 00:09:06.540 00:09:11.789 Aakash Tandel: Yeah, that makes sense. Are we billing project management? Time? Is that bill to the client

70 00:09:12.930 00:09:30.790 Nicolas Sucari: I’m not sure I mean I think we’re I mean we should right. We should build that hours, too. I don’t know if billing that yet or not. But we can set that to like if I go to settings to roles on reports roles and seniority here.

71 00:09:31.214 00:09:43.550 Nicolas Sucari: like each role can be set as non billable or available. Right? So for project managers, I have it billable. But if we don’t want to track that as billable. I can just click here and update. Okay.

72 00:09:44.130 00:09:54.019 Nicolas Sucari: like, that’s something that we need to define if we’re gonna build it ours or not. And we can use. For example, operations manager. I like this is my kind of role on Ops, and it’s not billable right?

73 00:09:55.080 00:09:59.179 Nicolas Sucari: Same as the internal roles. The designer. Like Ann Anna.

74 00:10:00.040 00:10:01.500 Nicolas Sucari: They they are not built.

75 00:10:03.320 00:10:13.620 Nicolas Sucari: The other ones are yeah available content manager. This is Ryan doing all of the content of the of Prime Virgin, Linkedin and other social media stuff is unavailable. Okay.

76 00:10:14.924 00:10:40.559 Nicolas Sucari: I’m just using roles. I’m not using seniorities yet. I mean, we can set this up, too. And what this has is we can then create like, you can have a primary role, additional roles. And you can have skills. And if we then create some projects with specific roles with skills. We can then suggest, like, which team member kind of suits better in those kind of roles and skills that we need for that project. Okay?

77 00:10:41.450 00:11:02.890 Nicolas Sucari: But for you guys, I mean, you should be able to see kind of this view with the timelines. Try to check on the projects and people if you want to go to people. So yeah, cash, I think you started on March right? I have you added like internally. But I if I want to add you to to a different project, I can go and add you to more projects.

78 00:11:03.150 00:11:07.129 Nicolas Sucari: For example, let’s say I think it’s Eden right

79 00:11:07.690 00:11:09.339 Aakash Tandel: Yep edenjabi. Yep.

80 00:11:10.040 00:11:13.110 Nicolas Sucari: So I can add you here as a project manager.

81 00:11:14.310 00:11:16.320 Nicolas Sucari: I’m gonna add you.

82 00:11:16.790 00:11:20.459 Nicolas Sucari: So this is, gonna say, Hey, you’re going over hours.

83 00:11:20.590 00:11:25.519 Nicolas Sucari: But yeah, let me sign. For example, when are you starting like this week? Are you starting with this program?

84 00:11:27.450 00:11:32.350 Nicolas Sucari: Okay? And how many hours a week is gonna be with each like 50% of your time

85 00:11:32.860 00:11:34.309 Aakash Tandel: Yeah, 50%

86 00:11:35.270 00:11:37.499 Nicolas Sucari: Okay? And you’re working 20 HA week, right?

87 00:11:37.790 00:11:38.400 Aakash Tandel: Yep.

88 00:11:39.010 00:11:42.600 Nicolas Sucari: So that’s that’s how we are kind of assigning it. Here.

89 00:11:42.760 00:11:45.520 Nicolas Sucari: I’m gonna leave it open ended, or even

90 00:11:45.760 00:11:52.900 Nicolas Sucari: so, I’m gonna assign you here. And, Steven, I’m gonna edit these. I’m gonna choose the end to be yesterday. Let’s say right?

91 00:11:53.230 00:11:54.360 Nicolas Sucari: Annotate. So yep.

92 00:11:55.370 00:12:08.920 Nicolas Sucari: Okay. So now it will say, Hey, it it you have like a red line under your time slots, and this means, like you are overbooked like you are still like having more than your 100 allocated

93 00:12:09.500 00:12:13.800 Nicolas Sucari: and this is because if we go to the internal one

94 00:12:14.720 00:12:25.760 Nicolas Sucari: or wait, I can show you on people. Yeah, here, you see, you were 100% assigned until yesterday. And since today you are 150. And what this means is.

95 00:12:26.200 00:12:35.730 Nicolas Sucari: let me go. Yeah, you mean, here you have a hundred percent internally and 50%. Even. So if I’m gonna I can click here, I can click end.

96 00:12:36.900 00:12:41.249 Nicolas Sucari: So I ended your like assignation for the internal project

97 00:12:41.550 00:12:48.579 Nicolas Sucari: to like from today. And now you have, like 50% on Eden. Only. So I can add you also to

98 00:12:50.530 00:12:51.780 Nicolas Sucari: Javi, right

99 00:12:52.090 00:12:52.710 Aakash Tandel: Yep.

100 00:12:53.730 00:13:01.340 Nicolas Sucari: So okay, I’m gonna add it to joby is 50% location starting today and open ended, okay.

101 00:13:02.790 00:13:03.870 Aakash Tandel: Oh, yeah, that was good.

102 00:13:04.680 00:13:08.209 Nicolas Sucari: So now you’re 100% assigned to

103 00:13:08.360 00:13:18.870 Nicolas Sucari: this is how it works right for everyone. So Akash is like that. But then, Amber, if you want to see yourself. You have like 25% on Nbc.

104 00:13:19.320 00:13:36.129 Nicolas Sucari: Some, I think you have 5 HA week for pool parts and 10 HA week for startlets. So 1010, and 5, I think you’re still. You still have some time. That’s because you have 40 h per week allocated. And you’re just allocating. I think it’s yeah, 25, right?

105 00:13:36.970 00:13:38.569 Amber Lin: Hmm! I see

106 00:13:39.650 00:13:54.889 Nicolas Sucari: So like this is how it works. If you guys like need to like add some kind of internal project, we can add it like to an internal project so that you can see like a 100. Or it’s up to you to to just like kind of decide how you wanna kind of be

107 00:13:55.201 00:14:12.340 Nicolas Sucari: allocating to those other projects. But this is how this tool works. When you assign all of the people. So, for example, let’s go to a wish. So Aish is 100% on pool parts. He’s only working. Yeah, it’s 100% of 10 HA week, as it says here.

108 00:14:12.724 00:14:32.590 Nicolas Sucari: So yeah, he’s like, fully booked with full parts for now. And we can obviously add like end dates and and split these kind of work between other projects. And we can set that up all from here. Right? Oh, sorry. This was. Yeah. So he has Eden and Javi.

109 00:14:32.680 00:14:55.239 Nicolas Sucari: I I have, Javi ended here because we set up a project like only for the 1st quarter but I can like make it open ended, too. I don’t know if if it’s gonna be better to have, like only one project for the client or kind of create different projects for the different quarters or renewals of us as the contract was were set up. Okay.

110 00:14:55.940 00:15:01.780 Nicolas Sucari: But we can talk that with them, and just have, like one project. And I can kind of extend this assessation

111 00:15:01.900 00:15:05.800 Nicolas Sucari: open-ended if you want, you see.

112 00:15:08.280 00:15:12.322 Nicolas Sucari: Okay, so that’s all of like, how we are allocating resources.

113 00:15:12.820 00:15:20.829 Nicolas Sucari: this is like a really good view. I guess. We can also have out of office stuff in here. We need to figure out how to kind of.

114 00:15:21.629 00:15:43.689 Nicolas Sucari: Yeah, we’re we’re thinking with them on how to have the out of office kind of asks in linear and then approving that. And then having that come here to just reflect when someone’s gonna be out of office. And ideally like this is the view that we should like. This is the what we should kind of review once a month, let’s say.

115 00:15:43.690 00:15:52.819 Nicolas Sucari: or with a different frequency, so that we can plan ahead of the week of, and see how the projects are gonna be

116 00:15:52.990 00:15:56.269 Nicolas Sucari: covered by the different roles and people that we have here. Okay.

117 00:15:57.310 00:16:07.270 Aakash Tandel: Yeah, I think Amber and I will probably look at this on a weekly basis. Either at the end of the week or at the beginning of the week, just because we’ll want to know if people are at office, or whatever

118 00:16:07.980 00:16:20.610 Nicolas Sucari: Exactly. Yeah. I mean, if you’re if you’re gonna be reviewing this on a Friday and you’re gonna be understanding that next week you’re gonna be missing like one or 2 people. That’s not good. That’s why I’m I’m I’m saying, kind of we need to review this like

119 00:16:20.700 00:16:38.030 Nicolas Sucari: way ahead, or maybe like 2 weeks ahead. And that’s something that we need to set up with the out of office kind of policy, right? Like to just try to ask for an out of office with a little bit of yeah, ahead of time and not just like the day before you’re leaving. Right?

120 00:16:39.610 00:16:50.600 Nicolas Sucari: Okay? So that’s the timeline. And then if you want to check like, how many hours are we spend actually spending compared to these planned hours that we have here. We can see

121 00:16:51.880 00:16:56.789 Nicolas Sucari: here in these reports, tab where we have, like all of the projects.

122 00:16:57.297 00:17:02.570 Nicolas Sucari: And if we go to projects, yeah, let me visit this editors.

123 00:17:03.760 00:17:24.159 Nicolas Sucari: Okay? So here we can see for each of these projects the assimination that we have. This is the 1st number. This is the plan at the planned amount of hours depending on the amount of roles and people that we have, and that allocation that we set in the timeline. And this is the actual time spent that’s coming from clock. If I right.

124 00:17:24.369 00:17:29.669 Nicolas Sucari: So if we want to go, for example, on Eden and let’s focus on March. Let’s say

125 00:17:29.860 00:17:32.280 Nicolas Sucari: so. Let’s go to this month. Okay?

126 00:17:34.590 00:17:47.909 Nicolas Sucari: So in March we have for let’s go. Eden. We have 224 h planned. We’re still like mid march, or almost yeah, one week before ending. And we only spend like 108.

127 00:17:48.080 00:17:58.089 Nicolas Sucari: This is just taking 2 weeks, because I need to upload like the last week here. But this is how like we can see this. And if we open this, we can see per people. Yeah.

128 00:17:58.350 00:18:06.009 Nicolas Sucari: so yeah, we can see, okay, so you have a cash like 12 h to spend on this project piece, because I, you started today, right

129 00:18:06.322 00:18:32.050 Nicolas Sucari: and we have one week, and I think 2 days, or something more next week to end the month. And that’s how this is like kind of comparing and we can compare like each people and see who’s spending more than the time plan, who is spending less and yeah, get some insights on what we need to ask the client, or if we need to. Yeah, just understand why we’re spending more or less on each of these. Okay.

130 00:18:32.870 00:18:45.030 Amber Lin: A similar question on this is not for the operating system, but more so on clockified do we have access to see how much our team has been spending on each task.

131 00:18:45.860 00:18:47.000 Amber Lin: I don’t think it’s great.

132 00:18:47.000 00:18:50.629 Amber Lin: I don’t think I can see which of the team members it is

133 00:18:50.630 00:18:55.630 Nicolas Sucari: So you, if you, if you can access, clockify, and go to these reports, table like reports, tab

134 00:18:56.391 00:18:59.820 Nicolas Sucari: You can. Then, for example, let’s say this month.

135 00:18:59.960 00:19:06.170 Nicolas Sucari: Okay, and let’s go to one project. Let’s say, Eden, we’re looking at that.

136 00:19:07.780 00:19:19.160 Nicolas Sucari: I don’t know if you have access to this view, but if not, I’m gonna yeah. We can just ask Utah to give you access. You can track by user. And you can see here, like, for example, Sahana’s been spending 61 h right

137 00:19:19.450 00:19:19.850 Amber Lin: Twice.

138 00:19:20.143 00:19:28.660 Nicolas Sucari: And and if you wanna go like for these details, we can go to the detail view, and we can see by task like, which are the tasks that

139 00:19:29.860 00:19:36.259 Nicolas Sucari: like sorted out yeah, by duration. Okay, so this was like the most

140 00:19:36.450 00:19:46.290 Nicolas Sucari: time spent task that has been working on. For example, 7 h on redoing the marketing dashboard, build a mobile version and profitability dashboard.

141 00:19:46.490 00:19:47.260 Nicolas Sucari: is he?

142 00:19:50.350 00:19:52.550 Nicolas Sucari: And we can do this for all clients.

143 00:19:53.030 00:19:55.270 Nicolas Sucari: and you have access to this

144 00:19:55.640 00:19:57.840 Aakash Tandel: Yup, yeah. Amber. Do you have access

145 00:19:58.110 00:20:06.610 Amber Lin: Yeah, let me just share my screen to never sure. Let me share my screen to just make sure

146 00:20:08.770 00:20:13.499 Nicolas Sucari: But the idea with operating on clockify is, yeah, right now, I’m doing it manually.

147 00:20:13.984 00:20:33.709 Nicolas Sucari: It’s just like exporting this view. Deleting some columns and doing some, yeah, just clean up of that data and uploading the Csv to operating. But yeah, the idea is that you can go into operating review the location the same week and see how how much time do we have left, or what what is happening

148 00:20:33.820 00:20:35.980 Amber Lin: To each of those projects. Right?

149 00:20:36.320 00:20:40.580 Amber Lin: If you go, if you want details, you you yeah, you need to go to clockify. I guess

150 00:20:40.840 00:20:50.029 Amber Lin: I feel like I have a feeling that my team, like Miguel and Casey, are not putting it in this project.

151 00:20:50.440 00:20:50.970 Amber Lin: Yes.

152 00:20:50.970 00:20:52.319 Nicolas Sucari: So yeah, if you wanna if

153 00:20:52.580 00:20:57.099 Nicolas Sucari: if you want to see what case is being like kind of logging into, go to reports

154 00:20:58.870 00:21:03.829 Nicolas Sucari: Go back to reports. Clean the the one that says project, do you? Wanna yeah, clean that up

155 00:21:04.280 00:21:07.129 Nicolas Sucari: and just a filtering team.

156 00:21:07.660 00:21:14.150 Nicolas Sucari: Look for Casey there, yeah, and click, apply filter.

157 00:21:15.390 00:21:17.830 Nicolas Sucari: So, Casey. And if you check, if

158 00:21:18.277 00:21:21.409 Amber Lin: Does not break it down, it seems.

159 00:21:21.450 00:21:23.460 Amber Lin: Yeah, I’m about to click on

160 00:21:24.060 00:21:26.099 Nicolas Sucari: Yeah, exactly. So he’s been working.

161 00:21:26.450 00:21:26.850 Nicolas Sucari: ABC,

162 00:21:27.350 00:21:28.959 Amber Lin: That’s so funny.

163 00:21:28.960 00:21:30.640 Nicolas Sucari: Yeah, he’s been adding that to it.

164 00:21:30.640 00:21:31.130 Amber Lin: Okay.

165 00:21:31.780 00:21:47.500 Amber Lin: I see. Okay, maybe once we consolidate the operating, I think we should also tell our team. Okay, how do you lock the time properly, because we can’t really track. They’re not putting it in the right place.

166 00:21:48.280 00:21:59.139 Nicolas Sucari: Yeah, yeah, of course. I mean, it’s just like, if you go to the clock. If I if you go into timesheet or time tracker. You need to select the project, and that’s how kind of we are

167 00:21:59.500 00:21:59.950 Amber Lin: Yeah.

168 00:21:59.950 00:22:03.880 Nicolas Sucari: He’s he’s logging in AI automation, and he’s not logging in ABC.

169 00:22:04.210 00:22:04.690 Amber Lin: That’s good.

170 00:22:04.690 00:22:29.689 Nicolas Sucari: Change that we need to do. We can go back and do that changes if if you need. Obviously like, we can override what he’s been logging. But yeah, I mean, we need. That’s that’s why I mentioned that on Monday, like, it’s really important to track correctly the time spending clock. If I because clock, if I is kind of our source of of time spent right? If that’s not correct, then uploading it to anywhere. It’s gonna be wrong

171 00:22:30.710 00:22:36.065 Aakash Tandel: Yeah, amber. I would reach out to people directly if they’re not doing it correctly in

172 00:22:36.900 00:22:42.060 Aakash Tandel: o’clock, if I cause I’ve I’ve just looked at Javi and Eden. It looks like everyone’s doing correctly. So

173 00:22:42.060 00:22:42.509 Aakash Tandel: oh, good!

174 00:22:42.700 00:22:45.069 Aakash Tandel: Go ahead and ping people directly like just

175 00:22:45.070 00:22:48.456 Amber Lin: Yeah, let me let me write that down

176 00:22:49.750 00:22:56.759 Nicolas Sucari: If you need my help, let me know amber, I can. Yeah, I can go. And just like, meet with Katie and try to guide him on how to do it. If you want

177 00:22:56.760 00:23:02.730 Amber Lin: I think this is fine. It’s pretty pretty straightforward, just a little bit more than what they’re doing right now.

178 00:23:03.190 00:23:03.840 Amber Lin: so I’ll talk.

179 00:23:03.840 00:23:04.240 Amber Lin: But

180 00:23:06.730 00:23:15.290 Aakash Tandel: Yeah, I don’t. And it might be helpful just to give like brief blurbs, like, it looks like some people are doing details. Some people are not. I think it’s helpful if they do that. So just, you know.

181 00:23:15.890 00:23:16.690 Aakash Tandel: that might be good

182 00:23:16.690 00:23:22.900 Amber Lin: Yeah, maybe you can post in the brain force team of what we expect for how people lock their time

183 00:23:23.600 00:23:28.310 Nicolas Sucari: Yeah, yeah, maybe I can create a documentation and share that also.

184 00:23:29.790 00:23:32.489 Amber Lin: Okay, okay, that’s all the questions from my side.

185 00:23:33.620 00:24:02.259 Nicolas Sucari: Cool. Then. Obviously, if we can. If you wanna start kind of reviewing these information on operating every week, let me just kind of let’s set a meeting I can join. We can go quickly through all of the teams and see how that weeks how that week is gonna go, or the next week until you guys feel that you can handle that yourselves. And yeah, I’m I’m still kind of adding, like, I’m trying to have all the information from

186 00:24:03.051 00:24:23.889 Nicolas Sucari: everyone like when they started working at Brainforge and doing that like super detailed so that we know exactly all of all of all of those kind of all of the availability. And finally, what I’m trying to do is to add all of the rates, billable rates that we have for each client, so that we kind of go deeper into financials. Using this app

187 00:24:25.070 00:24:44.130 Amber Lin: I mean, Akash. What do you think about? Maybe Friday we can meet as a team and look at people’s availabilities. I think by then Nico will have more details there and then we’ll know the team a bit better. And then Friday, we can say, Okay, how’s the allocation been this week. And what do we want it to be? Next week we could do other Pm. Retro

188 00:24:44.430 00:24:55.319 Aakash Tandel: Yeah, that’s what I was. Gonna say, I was Nico, we’ll probably do at the beginning of Pm. Retro, and then you can hop off after we just go through the operating, just to make sure we’re all on the same page that probably make the most sense

189 00:24:56.000 00:24:58.899 Nicolas Sucari: Okay. When when are you having the Pm. Retro on Fridays?

190 00:25:01.264 00:25:10.030 Aakash Tandel: They’re typically. So I I gotta actually work on time for me, too, because, like 5 to 6 pm. On Friday is a little hard for me.

191 00:25:10.030 00:25:10.879 Amber Lin: Because that’s Eastern

192 00:25:10.880 00:25:11.420 Nicolas Sucari: Okay.

193 00:25:12.160 00:25:13.640 Aakash Tandel: So I

194 00:25:13.640 00:25:21.900 Amber Lin: A little bit earlier, because it’s just me you and Utah essentially, and Utah may not come. So just look

195 00:25:21.900 00:25:22.299 Nicolas Sucari: Oh, because

196 00:25:22.300 00:25:26.329 Amber Lin: My calendar is up to date, so just move it around as you as you’re free

197 00:25:27.920 00:25:29.120 Nicolas Sucari: Okay. Yeah.

198 00:25:29.414 00:25:32.060 Aakash Tandel: What’s your standard time? Is it? Eastern Standard time?

199 00:25:32.334 00:25:35.900 Amber Lin: I’m in. Pst, Nico, I think, is in a different time zone

200 00:25:36.090 00:25:43.170 Nicolas Sucari: I’m like 1 h ahead of est, but that’s fine like. Just think of me as I’m est

201 00:25:43.770 00:25:51.160 Aakash Tandel: Okay, cool. I’ll yeah, okay, that sounds good. That is late for both of us, then. So I’ll try to figure out, well, Amber and I can sync up and figure out a time that works for everyone

202 00:25:51.410 00:25:55.670 Amber Lin: Yeah, just pick a time on calendar. I’m all I’m open

203 00:25:55.930 00:25:57.660 Aakash Tandel: Okay, yeah, that sounds good.

204 00:25:57.911 00:26:18.320 Nicolas Sucari: Yeah, I I kind of asked Utam. If you want me to like share these in the because I see you have Monday and Fridays these kind of Pm planning on retro. Right? Yeah, that’s what I told him. Like, if you want, I can go on Monday and kind of share these. But that’s fine, like, let me know. What times that’s gonna be on Friday. And yeah, obviously, we can review that. And then I can hop on

205 00:26:18.630 00:26:19.110 Aakash Tandel: Okay.

206 00:26:19.870 00:26:20.650 Aakash Tandel: Sounds. Good.

207 00:26:21.310 00:26:21.820 Aakash Tandel: Awesome.

208 00:26:21.820 00:26:22.330 Nicolas Sucari: Thank you. Guys.

209 00:26:22.330 00:26:23.149 Aakash Tandel: Thanks for the overview

210 00:26:23.150 00:26:24.110 Amber Lin: Thank you.

211 00:26:24.440 00:26:25.040 Aakash Tandel: Talk to you soon

212 00:26:25.040 00:26:34.160 Nicolas Sucari: Let me know if you need anything else regarding this or any other stuff. I’m trying to work on all kind of operations with Marianne. So yeah, anything you need. Let us know

213 00:26:34.340 00:26:34.990 Amber Lin: Thank you.

214 00:26:34.990 00:26:35.520 Aakash Tandel: Good.

215 00:26:35.910 00:26:36.330 Amber Lin: Bye.

216 00:26:36.330 00:26:37.829 Nicolas Sucari: Thank you. Guys. Bye, bye.